What a Custom Home Build Actually Looks Like

Download PDF Version

A realistic timeline - not the optimistic one, the honest one.

I have built homes that came in ahead of schedule and homes that ran long. The projects that stay on track share one thing: an owner who understood the timeline before the first shovel went in the ground.

The other thing that kills timelines is mid-build value engineering. A budget conversation that turns into material substitutions, which turns into waiting for approvals, which turns into schedule slippage. The way to prevent that is to make every material decision before construction begins, lock them into the contract, and hold the line. Here is what a well-planned build actually looks like.

MONTHS 1-2: PRE-CONSTRUCTION PLANNING

MONTHS 2-4: DESIGN DEVELOPMENT & PERMITS

MONTHS 3-5: SITE PREPARATION & FOUNDATION

MONTHS 5-7: FRAMING & ROUGH-INS

MONTHS 7-9: INSULATION & MECHANICALS

MONTHS 9-11: FINISH WORK & PUNCH LIST

MONTHS 11-12: CLOSEOUT & HANDOVER

OWNER TIMELINE CHECKLIST